Traffic Alerts

Traffic Updates for the Week of October 25th

 

Cedar Street Waterline and Reconstruction – The contractor will complete paving sidewalks and driveways next two weeks and will complete final clean up the following week.

 

Central Fire Station – The contractor will continue work associated with the construction of the new Fire Station.  

Central Maine Power will be relocating their facilities to the new poles starting Monday.  This work will require temporary road closures.

 

East Brunswick Overlay Contract The contractor has completed surface paving all roadways in East Brunswick, they plan to return next week to complete the overlay of Oak Street, final clean up will be completed next month.

 

Merriconeag Parking Lot – Public Works will begin laying out and constructing the recently approved Merriconeag Parking Lot. 

 

UPCOMING PROJECTS:

 

Due to global supply chain and labor shortages the below project has been postponed until spring.

 

October

Abijah and Hawthrone Street Watermain Replacement -  The Brunswick Topsham Water District will be replacing the watermain on Abijah and Hawthorne Streets.  Following the completion of the watermain the Town will overlay the roadways (Tentatively starting in August).

 

As always construction is weather dependent and subject to many variables, updates will be provided as they become available.