Central Fire Station – The contractor will continue work associated with the construction of the new Fire Station. At times temporary lane or road closures of Pleasant Street, Webster Street, and Turner Street may be necessary.
Church Road – Surface pavement will be placed at the start of next week. Additional work at the railroad crossing, driveway aprons, and remaining ADA improvements. The road will be reduced to one-way traffic during working hours as necessary.
Woodside Road, Raymond Road, Miranda Street – Woodside has been reclaimed and being prepared for pavement for next week. Driveway aprons on Raymond are being addressed to complete paving activities. Woodside and Raymond will be reduced to one-way traffic during working hours. Final touches on Miranda will be completed soon.
Armory Street –The contractor will strip and repave Armory Street. The road will be local traffic only during construction.
Weymouth Street – The sewer district will be performing small repairs. The contractor will strip and repave the dead-end portion of Weymouth Street. The road will be local traffic only during construction
Upcoming Projects:
Baribeau Drive – The contractor will be overlaying the road and upgrading pedestrian ramps to be ADA compliant. Sections of the road will be reduced to one-way traffic during working hours.
Bath Road Culvert Replacement – Bids for the replacement of a culvert running under Route 1 on Bath Road are due in September. Coordination with utility companies for their existing infrastructure is being performed. This project will require a coffer dam to be constructed at either end of the existing culvert and bypass pumps will be set up. The existing culvert at Thompson Pond will be replaced. During construction, a stretch of Bath Road between Sunnybrook Senior Living and Mallet Springs Water & Ice will be reduced to one-way traffic.
Graham Road – The contractor will overlay the road. The road may be reduced to local traffic only during construction.
Hacker Road – The contractor will overlay the road with localized full depth repairs. Sections of the road will be reduced to one-way traffic during working hours.
Lisbon Road – The contractor will overlay the road. Sections of the road will be reduced to one-way traffic during working hours.
As always construction is weather dependent and subject to many variables, updates will be provided as they become available.